P=Planning W=Waterside T=Terminal L=Landside
| PROJECT LOCATION/DESCRIPTION | PROJECT TYPE | COST ESTIMATE ($000) |
|---|---|---|
| Other Port Projects Under Construction or Expected to Be Under Construction by 10/2003 (commencement of TEA3 term) Costs Not Included in Total | . | . |
| Harry Bridges Realignment ($20 M) | L | . |
| Pier 400 Phase 2 ($118 M) | T | . |
| West Basin Development Phase 2 ($111 M) | T | . |
| World Cruise Terminal berths 93A & B ($14 M) | T | . |
| Main Channel Deepening Program ($165 M) | W | . |
| San Pedro Waterfront Red Car Line ($7 M) | L | . |
| Near | . | . |
| Portwide Wharf Upgrade Program Phase I | W | $100,000 |
| Berths 226-232: 55 acre expansion | T | $15,000 |
| Portwide Security Program | W,T | $50,000 |
| Berth 142-147 ICTF Rail Yard | L | $20,000 |
| Avalon Grade Separation | L | $20,000 |
| Neptune Avenue Grade Separation | L | $30,000 |
| Navy Way/Seaside Avenue Grade Separation | L | $20,000 |
| 110/47/103 Interchange Improvements | L | $50,000 |
| Berths 136 – 148 Container Development | T | $120,000 |
| Berths 223 – 236 Evergreen Expansion | T | $10,000 |
| Manual Rail Yard – Pier “A” replacement | L | $12,000 |
| Catalina Terminal and Island Helicopter Terminal | T | $15,000 |
| West Channel/Cabrillo Marina | W | $16,000 |
| Mid | . | . |
| Berth 195-199 Container Terminal | T | $132,000 |
| Portwide Wharf Upgrade Program Phase II | W | $100,000 |
| Waterfront Redevelopment Program | W | $420,000 |
| West Basin Rail Yard Expansion | L | $20,000 |
| B Street Rail Realignment | L | $3,000 |
| Pier 300 40-acre Terminal expansion | T | $40,000 |
| Berths 206 – 209 Container Development | T | $80,000 |
| SUBTOTAL: Port of Los Angeles | . | $1,273,000 |