SOUTHERN CALIFORNIA MTS

Infrastructure Needs Assessment

PORT OF LONG BEACH

High-priority ‘Strategic Investments’ are BOLDED.

P=Planning    W=Waterside    T=Terminal    L=Landside

PROJECT LOCATION/DESCRIPTION PROJECT TYPE COST ESTIMATE
($000)
* Other Port Projects Under Construction or Expected to Be Under Construction by 10/2003 (commencement of TEA3 term) Costs Not Included in Total . .
POLB/POLA Advanced Trans.Mngt Info/Security System ($7.8 M) L .
Terminal Island Freeway/Ocean Blvd Interchange ($50 M) L .
Pier G, Berths G212 – 215 upgrades ($10 M) W .
Pier T Container Terminal – Phase II (200.3 M) T .
Pier G Container Terminal – Phase I ($80 M) T .
Pier E Container Terminal – Phase I ($20.7 M) T .
North Harbor Storage Facility ($1.7 M) T .
Alameda Corridor Terminus - Mainline Trackage ($11.9 M) L .
Near . .
Ports Security Project T $20,000
Pier S Container Terminal T $140,200
Terminal Island Fire Station T $2,000
Pier T EastBreak Bulk Facility T $12,700
Pier T East Liquid Bulk Facility T $20,000
Pier J South Phase I T $80,000
Gerald Desmond Bridge Replacement/I-710 Corridor Project- also listed under L.A. region Highest Priority L $605,000
Terminal Island Freeway/Ocean Blvd Interchange -shortfall L $15,000
Alameda Corridor/Pier B St. Railyard Expansion L $67,000
POLB/POLA Advanced Transportation Management Info/Security System -shortfall L $3,100
I-710 Southern Terminus Bridge Rehab project L $22,600
Pier B Street/Terminal Island Fwy On-Ramp L $1,000
Alameda Corridor Terminus/Port Rail Mainline System L $19,400
Mid . .
Pier G Container Terminal – Phase II T $319,000
Pier J Container Terminal T $337,000
Pier E Container Terminal - Phase II T $308,200
Pier A Container Terminal T $189,300
Pier B Auto Terminal T $12,100
Main Channel Dredging - Phase II W $2,000
Alameda Corridor Terminus/Port Mainline Rail System Cerritos-Centralized Train Control L $34,600
Long . .
Pier W Container Terminal T $500,000
Alameda Corridor South End Improvements (add'l trackage; Cerritos Channel, New Dock St./Henry Ford Av. grade sep.) proposed joint POLA/POLB project L $75,000
SUBTOTAL: Port of Long Beach . $2,785,000